A bond completion project with a tri-party agreement between the District, the surety and Blois Construction. Extensive project management, coordination and communication was required to complete this project that had been partially completed by a prior contractor. Concrete demolition and repair, mechanical piping, HVAC, exhaust piping, misc. steel, fire sprinklers, generator and electrical were all a part of this project. Grading and paving was also required to complete civil improvements on adjacent city streets.
A fast track design-build project to increase the reliability of critical water delivery to the Santa Barbara coastal region. Design challenges included determining pipeline route through multiple easements, numerous environmental and biological requirements and approvals, historical landmarks and system design to meet hydraulic requirements of the system. Construction challenges included installing approximately 2,000 lf of 48" welded steel pipe in extremely steep and difficult terrain, protecting the fragile existing 60 year supply line and excavating through hard rock.
Installation of all wet utilities and street improvements, including curbs & gutter and AC pavement for the Playa Vista development. Coordination with other contractors, a fast track schedule and restoring and preserving the Ballona Wetlands were among the project management challenges. One of the most technical challenges was the installation of sewer lines below the ground water table in busy Jefferson Blvd at depths in excess of 30 feet.
Blois work included the complete installation of the storm drain, sewer, domestic water and fire water system for this facility designed to preserve classic and historical movies and films that deteriorate over time. Storm drains system included extensive subdrainage on the "living roof" of the facility and multiple sizes. Sewer lines were installed in very difficult circumstances, in conjunction with building shoring and up to depths of 30 feet.
A crowded, congested small site in the heart of the Santa Monica required intensive planning and multiple backup plans in order to meet the schedule. On and offsite sewer and storm drain were the heart of the project, with multiple connections to existing utilities. The offsite sewer included depths of over 30 feet deep in the main drag of Santa Monica, Ocean Ave. One of the more challenging items of work involved installing an offsite water line across and down Ocean Ave and right in front of the iconic Santa Monica Pier.
On and off site utility systems for the beautiful and innovative new home of the Conrad N. Hilton Foundation. Blois work included storm drain, sewer, domestic water, reclaimed water and irrigation. As part of the of the building LEED certification, Blois helped design and install an innovative "grey water" recovery system to be used for irrigation. 3D BIM modeling drawings and coordination were also part of our scope of work.
An innovative storm water retention and filtration system were the highlights on this project to expand the City of Santa Monica's public bus yard. The desire to keep all storm water runoff onsite required large underground retention vaults and filtration systems before discharging into the ground water. New sewer, water, firewater and gas were also installed for the new facilities. Pre-planning and coordination with the General Contractor was required due to phased construction intended to keep the existing facility in operation.
Blois Construction installed all of the storm drain, sewer and leach fields and domestic and fire water for this project at a reduced cost to help contribute to the building of this important facility. The National Disaster Search Dog Foundation is a not for profit organization with the mission to train and provide search dogs to assist in the rescue of victims of natural disaster worldwide. One interesting aspect of this project was the combining of confined space training for our crews with the training for the search dogs, utilizing the new storm drain system that we installed.
Complete replacement of existing utilities in Sony Studios "Main Street" at their Culver City studios. Storm drain, sewer, domestic and fire water and steel gas line systems were installed in extremely tight conditions and scheduling restraints. The studios production schedule required Blois to work seven days a week and double shifts. In addition, work locations and access were constantly changed to meet the studio's needs. Unknown or mis-marked existing utilities resulted in "on-the-fly" design changes and made for challenging work.
A project consisting of grading, canals, concrete structures, site piping, pumps and a control building to increase the Kern County Water Agency's flexibility in delivering water to its customers in the Central Valley. 250, 350 and 600 HP motors were installed in a concrete pump station designed for efficient water flow. Large steel and RCP pipe was installed between flow control structures with hydraulic slide gates controlling the flow. Coffer dams were used to control existing flows and make connections between new and existing canals under tight deadlines. A control building was built to house the SCADA system used to...
Pump station, piping and other facilities to discharge water treatment by products into the Calleguas Salinity Management Pipeline. The work included mechanical piping, valves, concrete vaults & wet wells, meters, chemical feed equipment & piping and chemical tanks. The most challenging aspect of the work was the excavation, shoring and construction of a cast in place wet well below the existing ground water table in very limited space.
Part of a project to increase group water supplies by over 40,000 acre-feet a year for the Calleguas Municipal Water District. Over 8,500 lf of 48" pipeline was installed in this segment to carry excess brine from the treatment process to the ocean. Due to the corrosive properties of the brine, never before used materials were incorporated into this project, including 48" C900 PVC fittings and required close coordination with the Owner and the Engineer. Other challenges included a 54" mirco-tunnel under an existing channel and extensive traffic control on a busy major road.
Installation of over 20,000 lf of welded steel pipe, varying for 10" to 42" in diameter in existing city streets, city bike paths and on 3 existing bridges crossing waterways. Construction easements on bike paths were very limited and had very tight and strict schedule milestone that had to be met to accommodate City events. Heavy traveled and high traffic streets required that 50% of the street work to be installed at night. Existing utilities required installation of the 42" steel pipe at depths of 20 to 25 feet deep in the busy intersections. Environmental and biological monitoring was required...
A very challenging job located in high risk and highly visible location. Located on the scenic Pacific Coast Highway at Will Rogers beach park, this project was one of the final stages of the City of Los Angeles' program to eliminate the discharge of polluted storm drain runoff into the Santa Monica Bay. The work included the installation of 42" Hobas pipe in PCH, mircotunneling underneath an existing flood control channel, siphon, deep shafts, sheet piling, secant piles, beam and plate shoring and extensive dewatering for the installation of pipe and structures well below the ground water level. Significant safety...
Over 3,550 lf of an exiting drainage channel was removed and replaced with a new 25 lf wide by 14 lf high concrete rectangular channel. Over 7,000 cubic yards of concrete, 850,000 lbs of steel and 100,000 cubic yards of excavation and removal were required to complete this project. Building the new channel required maintaining the flow in the existing channel while the new one was being constructed. Unexpected heavy rains in May caused extensive damage and required us to accelerate to complete the project before the winter rains hit.
Installation of approximately 9,000 lf of 24" welded steel pipe line in a narrow, heavily traveled main thoroughfare between Calabasas and the Pacific Coast Highway. Heavy traffic required restricted working hours and careful planning. The discovery of Native American artifacts required a switch from open cut construction to bore and jack for a portion of the job. One of the most challenging aspects of the job was the presence of an existing utility line running parallel to the new line, requiring careful and innovative shoring.
Installation of complete sewer, water and storm drain systems for the construction of new apartments. Tight coordination was required between the demolition of old and installation of new utilities and required multiple move on and offs and constant re-locating for area to area. Several infiltration pits were installed to limit the amount of runoff from the project to city streets.
On and off site utility improvements for new apartment complex, including sewer, storm drain and domestic and fire water. Off-site portion was installed in heavy vehicle and pedestrian traffic in the heart of Santa Monica's downtown tourist district. Limited working space and simultaneous neighboring projects required tight scheduling and pre-planning.
Complete sewer, water and storm drain system for a large home development. Blois' ample labor and equipment resources coupled with installing all major components of the underground utilities allowed us to coordinate and change phasing to match the owners changing requirements and tight schedule. Storm drain system included trenches over 40 lf in depth and excavation of native rock.
Sewer, Water, Storm Drain and Gas systems installed in tight coordination with other contractors on this fast track school project. Tough schedule constraints and small site made contract administration and control a necessity to meet project requirements.
Complete underground utility systems installed on difficult hill side locations. Installation in and amongst unknown existing utilities and constant plan changes made planning and flexibility a must for the completion of this project.
Installation of 4" to 14" chilled water and insulated hot water system to service buildings on the LMU campus. The project included valves, valve pits, paving, concrete and paving replacement and vehicle and foot traffic control. The entire installation had to be completed during the brief summer break for LMU students. Extensive preplanning, including submittals, traffic control, phasing and delivery of materials had to be done to ensure hitting the required milestones. Overtime and multiple crews were utilized to help meet the schedule. A tight job site had to be maintained in order to minimize the impact upon the campus...